Stonework Restoration - End of Week 1

The majority of the scaffolding was assembled by the end of Week 1.

On Monday a full survey will be carried out around the property and then the stonework restoration will fully commence.

Weekly updates to follow.



Wednesday, 15 April 2009

Stonework Restoration - Day 1

Scaffolding started to be assembled around the house today.

However, the scaffolders were a little different from anticipated.




More photos to follow later in the week.

Friday, 10 April 2009

Stonework Restoration Starts


Tuesday 14th April 2009 - A Date In The Lamlash House Diary!

After three years of negotiation and planning, a programme of stonework restoration will start at Lamlash House on Tuesday 14th April 2009.

Scaffolding will go up around the building and the work will take around 8 weeks to complete.